PROJECT MANAGEMENT & DEVELOPMENT
The Property Development module is an end-to-end operating environment for planning, controlling, financing, constructing and commercialising real estate development projects. It is designed to connect information that is often kept in separate spreadsheets, project-management tools, BOQ files, contractor records, marketing systems and email threads.
|
LEASEORA PROPERTY DEVELOPMENT Detailed User and Technical Operations Guide Plan • Budget • Build Teams • Manage Risks • Create BOQs • Compare Contractors • Track Construction • Analyse Markets • Model ROI • Finance • Market • Pre-Lease • Complete |
For real estate developers, project directors, quantity surveyors, construction teams, finance teams, marketers and management
Version 1.0 | July 2026
|
|
Purpose of this guide This guide explains how a real estate company can use Leaseora's Property Development module from project inception to completion. It combines plain-language operating procedures with a technical reference based on the models, controllers, services, events, notifications and AI tools supplied for the module. |
1 Purpose, Audience and Scope
The Property Development module is an end-to-end operating environment for planning, controlling, financing, constructing and commercialising real estate development projects. It is designed to connect information that is often kept in separate spreadsheets, project-management tools, BOQ files, contractor records, marketing systems and email threads.
|
Item |
Description |
|
Primary users |
Corporate landlords, property developers, project directors, project managers, quantity surveyors, finance teams, construction teams, marketers, sales teams and executives. |
|
Secondary users |
Contractors, external consultants, lenders and other stakeholders who receive assigned access or notifications. |
|
Core scope |
Project setup, phases, tasks, teams, risks, BOQ, contractors, BIM, construction progress, documents, market analysis, ROI, scenarios, financing, marketing, leads, pre-leasing, virtual staging, collaboration, AI and completion. |
|
Operational boundary |
Leaseora records and supports the company's workflow. It does not replace statutory approvals, professional engineering certification, legal review, quantity surveying sign-off or management approval. |
|
Terminology |
This guide uses Real Estate Company, Developer and Corporate Landlord for the organisation managing the project. |
|
|
Configuration note Menu labels, field names and available actions may vary slightly by subscription, staff permission or product update. The end-to-end responsibilities and control principles remain the same. |
What the module connects
· Project scope - type, location, budget, dates, images, currency and approved description.
· Planning - phases, dependencies, tasks, milestones and timeline.
· People - internal staff, consultants, contractors, assignments and performance.
· Cost control - BOQ, rate schedules, versions, quotes, budgets and actual spend.
· Risk - identified risks, impact, probability, mitigation and escalation.
· Delivery - BIM, construction updates, reports, trends and project health.
· Feasibility - market intelligence, ROI, NPV, IRR, payback and scenarios.
· Financing - lenders, applications, terms, status and recommendations.
· Commercialisation - campaigns, leads, units, applications and virtual staging.
· Governance - documents, comments, activity logs, notifications and final exports.
2 End-to-End Module Overview
Figure 1. Property Development lifecycle in Leaseora
Recommended menu areas
|
Menu area |
Primary purpose |
|
Dashboard / Overview |
Portfolio and project KPIs, budget, progress, risks, tasks, predictions and preferences. |
|
Projects |
Create, edit, view, complete and export development projects. |
|
Phases & Timeline |
Structure work into phases and dependencies and view the Gantt timeline. |
|
Tasks |
Assign, prioritise, track, time-log and escalate work. |
|
Team |
Create project roles, assign staff and consultants, analyse gaps and export rosters. |
|
Risk Management |
Maintain the project risk register and mitigation plans. |
|
Bill of Quantities |
Create BOQ sections and items, version documents, compare bids and export. |
|
Contractors |
Register contractors, manage bids and evaluate performance. |
|
Construction Progress |
Publish updates, milestones, reports, trends and scheduled reporting. |
|
BIM Integration |
Upload, view, compare, preview, export and download BIM models. |
|
Documents |
Store permits, contracts, drawings, certificates and reports. |
|
Market Analysis |
Review location trends, demand, supply, prices and comparative markets. |
|
ROI & Scenarios |
Model project returns and compare optimistic, base and pessimistic outcomes. |
|
Financing Marketplace |
Browse lenders, apply for financing and track applications. |
|
Marketing & Leads |
Run campaigns, integrate platforms, score leads and analyse demand. |
|
Pre-Leasing / Unit Sales |
Create units and manage pre-lease or pre-sale applications. |
|
Virtual Staging |
Generate staged images, tours and marketing assets for unbuilt or empty units. |
|
AI Assistant |
Generate summaries, predict costs, review metrics and ask project questions. |
3 Phase 1 - Project Creation and Setup
Steps 1 and 2: create the project record and establish the control dashboard.
|
STEP |
Create a Development Project Primary user: Developer / authorised project administrator |
Navigate to Property Development -> New Project. Enter the approved project information and save the project with an initial status of Planning. The project becomes the central record to which all phases, tasks, risks, BOQs, contractors, documents, units and commercial activities are connected.
|
Field |
Purpose |
Good practice |
|
Project name |
Approved development name and phase. |
Use the formal project identity. |
|
Description |
Purpose, scope, unit mix and strategic value. |
Avoid claims not supported by approved information. |
|
Address / city / country |
Project location and currency context. |
Confirm country before financial modelling. |
|
Project type |
Residential, commercial, mixed-use, industrial or configured type. |
The type influences AI templates and recommendations. |
|
Budget |
Approved baseline project budget. |
Enter in the project currency and control who can edit. |
|
Start date |
Approved planned commencement. |
Use the current baseline programme. |
|
Estimated completion date |
Expected project completion. |
Update through controlled change management. |
|
Status |
Planning at inception. |
Move through approved lifecycle states. |
|
Feature image and gallery |
Project renders, site photographs and approved media. |
Upload authorised files and record image context. |
AI tools available at creation
|
AI tool |
How it helps |
Human control |
|
AI timeline suggestion |
Suggests a project duration based on type and scope. |
Project management reviews dependencies and constraints. |
|
AI phase suggestion |
Proposes common phases for the selected project type. |
Adapt to the approved delivery methodology. |
|
AI risk assessment |
Identifies early financial, regulatory, market and construction risks. |
Add owners and mitigation plans. |
|
AI budget allocation |
Suggests how the budget may be divided across phases. |
Finance and quantity surveying validate all figures. |
|
AI team suggestion |
Recommends project roles and composition. |
Management confirms availability, qualifications and accountability. |
|
AI financial plan |
Produces an initial financing and cash-flow outline. |
Treasury and finance validate. |
|
AI milestone suggestion |
Proposes major decision and construction milestones. |
Project manager approves dates and criteria. |
|
AI location analysis |
Reviews location factors and suggests opportunities. |
Use alongside professional feasibility and legal due diligence. |
|
AI type enhancement |
Adds type-specific detail to the project description and structure. |
Review before saving. |
|
AI image organisation |
Groups or orders project media. |
Confirm accuracy and access rights. |
|
|
AI is advisory AI suggestions should be treated as planning support. Final budget, programme, risk, location, team and milestone decisions remain with qualified and authorised professionals. |
Project creation checklist
|
☐ |
Project name, type and location are approved. |
|
☐ |
Budget and currency are correct. |
|
☐ |
Start and estimated completion dates match the approved programme. |
|
☐ |
Images and project description are authorised for use. |
|
☐ |
Project status is set to Planning. |
|
☐ |
Responsible project owner is identified. |
|
☐ |
Initial AI suggestions have been reviewed rather than accepted blindly. |
|
STEP |
Review the Project Dashboard Primary user: Project director / management |
Open the project dashboard after creation. The dashboard should provide one management view of budget, progress, tasks, risks, people, construction updates and AI insights.
|
Dashboard area |
Management question answered |
|
Budget vs actual |
How much was planned, committed and spent? |
|
Phase completion |
Which phases are pending, active, completed or overdue? |
|
Task progress |
What work is complete, blocked, due soon or overdue? |
|
Risk summary |
Which risks require immediate action? |
|
Team |
Who is assigned and where are capability or capacity gaps? |
|
Construction progress |
What is the approved completion percentage and trend? |
|
Timeline |
Are phase dependencies and milestones on schedule? |
|
AI insights |
What emerging patterns, costs or risks require review? |
|
KPIs and predictions |
How is project performance changing over time? |
At portfolio level, authorised users can review all developments, save filter presets, choose favourite projects, track KPIs, create predictions and maintain dashboard preferences.
4 Phase 2 - Project Phases and Timeline
|
STEP |
Define Project Phases Primary user: Project manager / planner |
Break the project into controlled phases such as Planning, Design, Approvals, Foundation, Superstructure, Building Envelope, Services, Fit-Out, External Works, Testing and Handover. Every phase should have an owner, dates, budget, status and clear completion criteria.
|
Field |
Purpose |
Control |
|
Phase name |
Clear stage of the development. |
Foundation. |
|
Start / end date |
Approved planned period. |
Used in timeline and overdue monitoring. |
|
Budget |
Phase-level budget allocation. |
Should reconcile to the project baseline. |
|
Description |
Scope and completion criteria. |
State deliverables, not only activity. |
|
Status |
Pending, In Progress, Completed or On Hold. |
Update only when evidence supports the change. |
|
Dependencies |
Predecessor or linked phases. |
Prevents unrealistic sequencing. |
AI support for phases
· Duration estimate - proposes a realistic duration using the project context.
· Risk assessment - highlights phase-specific threats and constraints.
· Phase template - suggests a reusable structure based on the project type.
|
|
Overdue control A phase is overdue when its approved end date passes before completion. Record the reason, impact and recovery action rather than changing the date without an approved baseline change. |
|
STEP |
Build and Optimise the Timeline Primary user: Planner / project manager |
Open the timeline view to see phases and milestones on an interactive Gantt-style schedule. Review dependencies, overlaps, resource conflicts and the effect of delays.
1. Confirm all phases have valid dates and dependencies.
2. Add key decision, procurement and construction milestones.
3. Review the critical sequence and potential resource conflicts.
4. Use AI optimisation as a scenario, not an automatic baseline change.
5. Approve the revised timeline through the company's change-control process.
Figure 2. Project status and supporting controls
5 Phase 3 - Task Management
|
STEP |
Create, Assign and Monitor Tasks Primary user: Project manager / team leads |
Tasks convert phase plans into specific accountable work. Every task should be linked to a phase and assigned to a responsible person.
|
Task field |
Meaning |
Good practice |
|
Task name |
Specific deliverable or action. |
Complete structural design review. |
|
Description |
Scope, acceptance criteria and supporting information. |
State what completion means. |
|
Assigned to |
Responsible team member. |
Use named accountability. |
|
Due date |
Expected completion date. |
Align with the phase and milestone. |
|
Priority |
Relative urgency. |
Use consistently across the project. |
|
Status |
Pending, In Progress, Completed or Blocked. |
Record blockers and recovery action. |
|
Phase |
Parent phase. |
Maintains reporting and timeline context. |
Task activities and time logs
PropertyDevelopmentTaskActivity records important changes and actions, while PropertyDevelopmentTaskTimeLog records time spent. These records help managers understand workload, delays and the actual effort required.
Task notification sequence
|
Event |
Recipient |
Purpose |
|
Task assigned |
Assigned member |
Confirms ownership and task details. |
|
Status changed |
Creator / manager |
Provides visibility of progress. |
|
Due soon |
Assigned member |
Prompts action before the due date. |
|
Overdue |
Assigned member and landlord |
Escalates delayed work. |
|
|
Blocked is not abandoned When a task is Blocked, record the blocking issue, owner, required decision and expected resolution date. A blocked task should remain visible until the constraint is removed or the task is formally changed. |
6 Phase 4 - Project Team Management
|
STEP |
Build the Project Team Primary user: Developer / project director |
Create project team records for internal staff and approved external consultants. Record role, contact information, specialisation and active status.
|
Field |
Purpose |
|
Name and contact |
Identifies the team member and communication details. |
|
Role |
Defines responsibility in the project. |
|
Specialisation |
Captures discipline or capability. |
|
Internal / external link |
Connects staff records or consultants. |
|
Status |
Active or Inactive. |
AI team tools
· Role suggestions - recommends roles based on project type and scale.
· Team analysis - identifies gaps, duplication or imbalances.
· Skill recommendations - suggests capabilities required for upcoming phases.
Use bulk status updates when several team members join or leave a project, and export the team roster for governance meetings.
|
|
Access follows responsibility A team record does not automatically mean unrestricted system access. Assign permissions separately and apply least-privilege access. |
7 Phase 5 - Risk Management
|
STEP |
Identify, Assess and Mitigate Risks Primary user: Project manager / risk owner |
Create a live risk register covering financial, construction, regulatory, environmental, market, procurement, health and safety and other project risks.
|
Risk field |
Required meaning |
|
Risk title |
Clear name of the uncertain event. |
|
Description |
Cause, event and potential consequence. |
|
Category |
Financial, construction, regulatory, environmental or configured category. |
|
Probability |
Low, Medium or High. |
|
Impact |
Low, Medium or High. |
|
Status |
Identified, Mitigating or Resolved. |
|
Mitigation plan |
Preventive, reducing, transferring or contingency actions. |
|
Owner |
Person accountable for monitoring and action. |
Risk workflow
1. Create the risk and assign an owner.
2. Rate probability and impact using the company method.
3. Define mitigation and contingency actions.
4. Link actions to tasks or phases where appropriate.
5. Review high-impact risks at management meetings.
6. Update status and evidence until the risk is resolved or accepted.
CurrencyConversionService can convert financial risk values into the chosen reporting currency. AI assessment and recommendations can support prioritisation, but management retains responsibility for risk acceptance.
|
|
High-risk escalation A high-impact risk should trigger prompt review. Do not close a risk simply because the due date has passed; close it only when the threat is resolved, no longer relevant or formally accepted. |
8 Phase 6 - Bill of Quantities (BOQ)
|
STEP |
Create and Control the BOQ Primary user: Quantity surveyor / authorised cost manager |
The BOQ engine structures project quantities, rates and costs into controlled sections and items. The BOQ can be created manually, imported or generated with AI assistance.
|
BOQ component |
Purpose |
|
BOQ header |
Project, client, consultant, date, revision and identification. |
|
Preamble |
Measurement rules, assumptions, inclusions and notes. |
|
Sections |
Work categories such as Earthworks, Concrete, Masonry, Services and Finishes. |
|
Items |
Description, unit, quantity, rate and amount. |
|
BOQ phases |
Optional connection between BOQ content and project phases. |
|
Rate schedule |
Reference rates used for pricing and comparison. |
|
Summary |
Section totals and overall BOQ value. |
|
Status |
Draft, Approved or Active. |
Recommended BOQ workflow
1. Create the BOQ and approved header.
2. Add preamble and measurement notes.
3. Create sections and line items.
4. Use auto-save while editing.
5. Review calculations and rates.
6. Create a version before major changes.
7. Compare contractor quotes against the BOQ.
8. Approve or activate only after authorised review.
9. Export to PDF or Excel for controlled distribution.
AI BOQ generation
BoqAIService can propose a BOQ using project type, size and location. The generated content is a draft and must be checked by a qualified quantity surveyor for scope, quantities, specifications, rates, local conditions and omissions.
|
|
Version before change Create a new BOQ version before making material revisions. This preserves the approved baseline and provides a clear history for audit, contractor comparison and claims review. |
9 Phase 7 - Contractor and Bid Management
|
STEP |
Register Contractors and Manage Bids Primary user: Procurement / project management |
Create contractor profiles containing company, specialisation, contact details, licence information and performance history. Contractors can be linked to bids for a project or BOQ.
|
Record |
Purpose |
|
Contractor profile |
Identity, company, specialisation, contacts and licence. |
|
Bid |
Commercial and technical submission linked to the project or BOQ. |
|
Bid status |
Submitted, under review, accepted or rejected according to configuration. |
|
Evaluation |
Performance record for quality, programme, cost, safety and communication. |
Bid workflow
1. Register or select the contractor.
2. Record the bid against the relevant project or BOQ.
3. Review scope coverage, price, programme, qualifications and risk.
4. Compare bid items with the approved BOQ.
5. Record clarifications and evaluation results.
6. Accept or reject the bid through an authorised decision.
7. Notify the contractor of the status.
|
|
Lowest price is not automatically best value Contractor selection should consider scope compliance, capability, programme, quality, safety, financial strength and risk, not price alone. |
10 Phase 8 - Construction Progress and Milestones
|
STEP |
Track Construction Progress Primary user: Construction team / project manager |
Post controlled construction updates showing the current approved progress percentage, update type, supporting description and media.
|
Update element |
Use |
|
Progress percentage |
Approved overall project or work-stage completion. |
|
Update type |
General, Milestone or Delay. |
|
Description |
Work completed, issues, decisions and next activities. |
|
Photos / videos |
Dated visual evidence approved for the audience. |
|
Milestone |
Key deliverable with planned and actual completion information. |
Milestone control
· Create milestones with clear completion criteria.
· Update milestone status only when evidence is available.
· Use overdue notifications to escalate missed dates.
· Link recovery actions to tasks and risks.
Reports and automated schedules
ConstructionProgressController can generate and manage progress reports. Reporting schedules can be created, executed immediately and used for recurring stakeholder updates.
Real-time and AI tools
|
Tool |
Purpose |
Control |
|
Real-time data |
Displays available live or frequently refreshed project data. |
Confirm source integrations and data freshness. |
|
Trend data |
Shows progress movement over time. |
Investigate unusual changes. |
|
Construction insights |
Highlights patterns and areas needing attention. |
Project team validates recommendations. |
|
Project health analysis |
Reviews progress, risk, cost and schedule indicators. |
Use as decision support. |
|
Apply suggestions |
Applies selected AI recommendations where supported. |
Require authorised review before change. |
|
|
Progress is not self-certified Leaseora records the percentage and evidence supplied by the company. The platform does not replace professional inspection, certification or statutory completion requirements. |
11 Phase 9 - BIM Integration
|
STEP |
Upload, View and Compare BIM Models Primary user: Design / BIM team |
Upload Building Information Models and link them to the correct project. Authorised users can open the viewer, generate previews, compare versions, export data, download files or remove obsolete models.
|
Action |
Purpose |
|
Upload |
Adds the approved BIM file to the project. |
|
Viewer |
Provides an interactive 3D view where supported. |
|
Preview |
Generates a visual reference image. |
|
Compare |
Shows two models side by side for review. |
|
Export / download |
Provides controlled access to model data or file. |
|
Delete |
Removes a model according to permission and retention rules. |
|
|
Model governance Use clear model naming, revision, discipline, date and status. Do not delete an approved model version if it is required for contractual, audit or as-built records. |
12 Phase 10 - Project Document Management
|
STEP |
Upload and Govern Project Documents Primary user: Project administrator / document controller |
Store contracts, permits, drawings, certificates, reports and other project records in one controlled document area.
|
Document category |
Examples / purpose |
|
Contracts |
Consultant, contractor, supplier, lender or other agreements. |
|
Permits and approvals |
Planning, environmental, building and statutory records. |
|
Drawings and specifications |
Approved design and construction information. |
|
Certificates |
Inspection, testing, insurance or completion evidence. |
|
Reports |
Progress, cost, risk, market and management reports. |
|
Templates |
Reusable controlled document formats. |
|
Legal documents |
Project-specific legal records. |
Document control practices
|
☐ |
Use a consistent document name, project code, revision and date. |
|
☐ |
Link each document to the correct project and category. |
|
☐ |
Restrict sensitive documents to authorised users. |
|
☐ |
Keep approved records separate from drafts. |
|
☐ |
Use update rather than uncontrolled replacement. |
|
☐ |
Retain deleted-document notifications and activity history where required. |
|
|
Deletion requires care A document should not be deleted merely because a new version exists. Follow the company's retention, legal and audit policy. |
13 Phase 11 - Market Analysis
|
STEP |
Analyse Development Markets Primary user: Development / research / investment team |
Use the market-analysis tools to evaluate a location before and during development. The module supports location reports, trends, market comparisons, custom analyses and aggregate statistics.
|
Capability |
Business use |
|
Location analysis |
Demand, supply, pricing, absorption and local characteristics. |
|
Trends |
Changes in price, demand, supply or activity over time. |
|
Compare markets |
Side-by-side review of multiple locations. |
|
Market report |
Structured analysis for decision-makers. |
|
Custom analysis |
User-defined assumptions and parameters. |
|
Unified dashboard |
Market insights alongside project performance. |
|
Refresh market data |
Updates information from configured sources. |
|
|
Data-source dependency Real-time market insight depends on configured data feeds, coverage and freshness. Verify the date, source and methodology before relying on market data for an investment decision. |
|
STEP |
Calculate Project Returns Primary user: Finance / investment team |
Enter land cost, construction cost, financing cost, expected sale or rental value and timeline assumptions. The ROI calculator can compute ROI, NPV, IRR and payback period and save the analysis.
|
Input |
Meaning |
|
Land cost |
Acquisition and related approved costs. |
|
Construction cost |
BOQ, preliminaries, contingencies and development costs. |
|
Financing cost |
Interest, fees and funding charges. |
|
Expected revenue |
Sale proceeds or rental cash flows. |
|
Timeline |
Cash-flow timing and project duration. |
|
Currency |
Project and reporting currency context. |
Financial outputs
|
Metric |
Plain-language meaning |
|
ROI |
Return relative to the investment cost. |
|
NPV |
Present value of projected cash flows after discounting. |
|
IRR |
Discount rate at which projected NPV equals zero. |
|
Payback period |
Time expected to recover the investment. |
AI insights can explain the results and identify sensitivity, but the finance team should validate assumptions, formulas, taxes, financing terms and timing.
|
STEP |
Create and Compare Scenarios Primary user: Finance / development team |
Create Optimistic, Base and Pessimistic scenarios using different assumptions for costs, timing, price, demand, financing or sales pace. ScenarioAIService can compare outcomes and highlight the assumptions driving the difference.
1. Create the Base scenario using the approved business case.
2. Create the Optimistic scenario with evidence-based upside assumptions.
3. Create the Pessimistic scenario with realistic downside risks.
4. Compare the scenarios side by side.
5. Review which variables have the greatest effect.
6. Agree contingency actions and decision thresholds.
15 Phase 13 - Financing Marketplace
|
STEP |
Browse Lenders and Apply for Development Finance Primary user: Finance / authorised director |
The financing marketplace allows the developer to browse registered lenders, view terms, submit applications and track application status.
|
Record |
Use |
|
Lender profile |
Rates, terms, products and available information. |
|
Application |
Project, amount, purpose, documents and requested financing. |
|
Status |
Submitted, under review, approved, rejected or configured stages. |
|
Metrics |
Marketplace and application performance indicators. |
|
AI recommendation |
Suggested financing options based on the project profile. |
|
|
Financing is subject to lender approval AI recommendations and marketplace access do not guarantee financing. The developer must review lender terms, security, covenants, costs, legal documents and repayment obligations. |
16 Phase 14 - Marketing Campaigns
|
STEP |
Create and Optimise Development Campaigns Primary user: Marketing team |
Create campaigns for the development with an approved name, budget, dates and target audience. Connect approved marketing platforms where integrations are available.
|
Campaign field |
Purpose |
|
Campaign name |
Identifies the project campaign. |
|
Budget |
Approved campaign spend. |
|
Start / end date |
Campaign period. |
|
Target audience |
Defined client or investor segment. |
|
Channels and assets |
Platforms, creatives and content used. |
|
Platform integration |
Connection data for social media, portals or configured tools. |
Campaign controls and AI tools
· Analytics - views campaign performance and channel results.
· Optimisation - suggests changes to targeting and spend.
· Audience insights - reviews likely audience attributes and behaviour.
· Competitive analysis - compares market and competitor activity.
· Recommendations - suggests campaign actions.
· Real-time analytics - uses connected data where available.
· Reports - exports, customises or schedules performance reports.
|
|
Platform connection control Test every marketing-platform connection before launch. Confirm account permissions, data access, tracking and privacy requirements. |
17 Phase 15 - Lead Qualification
|
STEP |
Capture, Score and Progress Leads Primary user: Marketing / sales team |
Leads from campaigns and other sources are stored as PropertyDevelopmentMarketingLead records. Maintain a complete profile, status, notes and supporting documents.
|
Lead status |
Meaning |
|
New |
Lead received but not yet worked. |
|
Contacted |
Initial communication completed. |
|
Qualified |
Lead meets the agreed criteria. |
|
Converted |
Lead progressed to an application or transaction. |
|
Lost |
Lead will not proceed; reason should be recorded. |
AI scoring can estimate lead quality and conversion probability. Pre-leasing analysis can also review lead quality and predict market demand from aggregated lead data.
Lead-management workflow
1. Capture or import the lead.
2. Assign ownership and record the source.
3. Review profile, need, budget and timeline.
4. Use AI score as a prioritisation aid.
5. Contact the lead and add notes.
6. Update status consistently.
7. Convert qualified leads to unit applications where appropriate.
8. Record a reason when a lead is lost.
18 Phase 16 - Pre-Leasing and Unit Sales
|
STEP |
Define Development Units Primary user: Sales / development administration |
Create the units available for pre-leasing or pre-sale. Each unit should have a unique number, type, floor, size, price and status.
|
Unit field |
Purpose |
|
Unit number |
Unique identifier. |
|
Unit type |
Apartment, office, retail, warehouse or configured type. |
|
Floor |
Physical location within the development. |
|
Size |
Approved measurement. |
|
Price |
Approved pre-lease or pre-sale amount. |
|
Status |
Available, reserved, applied, approved, sold, leased or configured status. |
|
Images |
Approved unit media. |
|
STEP |
Manage Unit Applications Primary user: Sales / leasing team |
Prospective clients submit applications for selected units. Review each application, supporting documents and lead history before approving, rejecting or waitlisting.
|
Action |
Meaning |
|
Approve |
Application accepted according to company policy. |
|
Reject |
Application will not proceed; record the reason. |
|
Waitlist |
Application retained pending availability or further decision. |
|
AI unit recommendation |
Suggests suitable units based on the lead profile. |
|
Reports / exports |
Provides a structured view of unit demand and application status. |
Figure 3. Commercial pathway from market analysis to unit applications
19 Phase 17 - AI Virtual Staging
|
STEP |
Generate Marketing Visuals for Unbuilt or Empty Units Primary user: Marketing / design team |
Virtual staging can generate images and tours for units that are not yet constructed or are unfurnished. Select the unit and generate staging using approved style and target-market guidance.
|
Action |
Use |
|
Generate |
Creates an AI-staged image for a unit. |
|
Recommendations |
Suggests staging style based on unit and market. |
|
Virtual tour |
Creates a tour using staged assets where supported. |
|
Compare |
Displays staged and unstaged versions. |
|
Export |
Downloads approved assets for marketing. |
|
Batch generate |
Creates staging for several units. |
|
|
Disclosure and accuracy Virtual staging should be clearly identified as illustrative where required. It must not misrepresent the final specification, dimensions, views, materials or included furniture. |
20 Phase 18 - Comments and Team Collaboration
|
STEP |
Collaborate on Project Records Primary user: All authorised project users |
Team members can comment on projects, tasks, phases and risks. Comments support discussion while keeping the context connected to the relevant record.
· Post a comment with a clear decision, question or update.
· Use @mentions for responsible team members.
· Reply in the existing thread rather than creating disconnected messages.
· Use reactions for acknowledgement where appropriate.
· Search comments to locate previous discussions.
· Export comment history when required for review or audit.
|
|
Comments do not replace formal approvals A comment can record discussion, but contractual changes, design approval, budget approval and risk acceptance should follow the company's formal governance process. |
21 Phase 19 - AI Project Intelligence
|
STEP |
Use the Central AI Assistant Primary user: Project director / authorised users |
PropertyDevelopmentAIController provides a central intelligence layer across the development. The assistant can review available project data and provide summaries, predictions and recommendations.
|
Capability |
Use |
|
Project summary |
Generates an executive overview of current project position. |
|
Cost prediction |
Estimates final cost from current spend and progress. |
|
Description |
Drafts a professional project description. |
|
Development programme |
Creates a project programme or brief draft. |
|
Project metrics |
Explains key project indicators. |
|
Recommendations |
Suggests actions across project dimensions. |
|
AI chat |
Answers project-related questions using available context. |
Figure 4. AI touchpoints across the module
|
|
Verify the source data AI quality depends on the completeness and accuracy of project records. Missing or outdated budget, progress, risk or task data can produce misleading recommendations. |
22 Phase 20 - Project Completion and Final Reports
|
STEP |
Mark the Project as Completed Primary user: Project director / authorised executive |
Set the actual completion date and change the project status to Completed only after the company has completed its internal handover, approvals, financial review and close-out requirements.
|
☐ |
All required phases are complete or formally closed. |
|
☐ |
Milestones are finalised. |
|
☐ |
Outstanding tasks and defects are resolved or transferred to a controlled close-out list. |
|
☐ |
Final construction and cost reports are available. |
|
☐ |
Risks are resolved, transferred or formally accepted. |
|
☐ |
Final BOQ and contractor records are retained. |
|
☐ |
As-built BIM and documents are stored where required. |
|
☐ |
Commercial and pre-leasing records are up to date. |
|
☐ |
Actual completion date is confirmed. |
|
☐ |
Stakeholders are ready to receive the completion notification. |
|
STEP |
Export Final Reports and Activity History Primary user: Project administrator / management |
Export the final project report and activity log for management, audit and project close-out. The report should summarise scope, programme, budget, phases, tasks, risks, contractors, construction progress, commercial outcomes and final status.
|
|
Completed does not mean records should be deleted Retain the project, documents, BOQ versions, models, reports and activity history according to the company's legal, contractual and retention requirements. |
23 Staff Roles, Permissions and Segregation of Duties
|
Role |
Typical responsibility |
Control point |
|
Executive Sponsor / Director |
Approves major budget, scope, financing, risk acceptance and completion. |
Should not rely only on AI or dashboard summaries. |
|
Project Director / Manager |
Controls phases, tasks, timeline, risks, progress and reporting. |
Major baseline changes require approval. |
|
Planner |
Maintains timeline, dependencies and milestones. |
Should preserve approved baseline history. |
|
Quantity Surveyor / Cost Manager |
Controls BOQ, rates, versions, cost reports and contractor comparison. |
AI BOQ must be professionally validated. |
|
Procurement Officer |
Manages contractor profiles, bids and evaluations. |
Selection requires authorised review. |
|
Construction Team |
Posts updates, milestones, evidence and reports. |
Progress should be verified. |
|
Finance / Investment |
Manages ROI, scenarios, financing and financial controls. |
Assumptions and calculations require review. |
|
Marketing / Sales |
Runs campaigns, manages leads, units and applications. |
Must use approved pricing and content. |
|
Document Controller |
Maintains document metadata, versions and retention. |
Sensitive records require restricted access. |
|
BIM / Design Team |
Uploads, reviews and compares model versions. |
Model status and revision must be clear. |
Recommended permission controls
· Use individual accounts and two-factor authentication where available.
· Grant access based on role and project responsibility.
· Separate BOQ preparation, review and approval.
· Separate contractor bid review from final award approval.
· Restrict financing, budget and ROI information.
· Restrict document deletion and project-completion actions.
· Review access when project roles change.
· Use activity logs for sensitive actions.
24 Status and Control Matrix
|
Record |
Typical status |
Control purpose |
|
Project |
Planning, In Progress, On Hold, Completed or configured states. |
Represents the overall development position. |
|
Phase |
Pending, In Progress, Completed, On Hold. |
Controls phase progress and overdue monitoring. |
|
Task |
Pending, In Progress, Completed, Blocked. |
Shows individual work status. |
|
Risk |
Identified, Mitigating, Resolved. |
Shows the risk-management position. |
|
BOQ |
Draft, Approved, Active. |
Controls cost-document authority. |
|
Contractor bid |
Submitted, under review, accepted, rejected or configured states. |
Records procurement decision. |
|
Lead |
New, Contacted, Qualified, Converted, Lost. |
Shows commercial progression. |
|
Unit application |
Pending, Approved, Rejected, Waitlisted or configured states. |
Shows pre-lease / pre-sale decision. |
|
|
Status must follow evidence A status should describe the real approved position. Do not use status changes only to make dashboards look current. |
25 Notifications Reference
|
Notification |
Recipient |
Trigger |
|
PropertyDevelopmentProjectCreatedNotification |
Landlord / Admin |
Project created |
|
PropertyDevelopmentProjectCompletedNotification |
All stakeholders |
Project completed |
|
PropertyDevelopmentProjectStatusChangedNotification |
Relevant stakeholders |
Project status changed |
|
PropertyDevelopmentPhaseCreatedNotification |
Team members |
Phase added |
|
PropertyDevelopmentPhaseStatusChangedNotification |
Team members |
Phase status changed |
|
PropertyDevelopmentPhaseOverdueNotification |
Landlord + Team |
Phase overdue |
|
PropertyDevelopmentTaskAssignedNotification |
Assigned member |
Task assigned |
|
PropertyDevelopmentTaskStatusChangedNotification |
Task creator / manager |
Task status changed |
|
PropertyDevelopmentTaskDueSoonNotification |
Assigned member |
Task due soon |
|
PropertyDevelopmentTaskOverdueNotification |
Assigned member + Landlord |
Task overdue |
|
PropertyDevelopmentMilestoneCreatedNotification |
Team members |
Milestone added |
|
PropertyDevelopmentMilestoneCompletedNotification |
Landlord + Team |
Milestone completed |
|
PropertyDevelopmentMilestoneOverdueNotification |
Landlord + Team |
Milestone overdue |
|
PropertyDevelopmentRiskUpdatedNotification |
Landlord / PM |
Risk updated |
|
PropertyDevelopmentHighRiskFlaggedNotification |
Landlord |
High-impact risk identified |
|
PropertyDevelopmentTeamMemberAddedNotification |
New member |
Added to project |
|
PropertyDevelopmentTeamMemberRemovedNotification |
Removed member |
Removed from project |
|
PropertyDevelopmentContractorBidReceivedNotification |
Landlord |
New bid received |
|
PropertyDevelopmentContractorBidStatusNotification |
Contractor |
Bid accepted / rejected |
|
PropertyDevelopmentDocumentUploadedNotification |
Team members |
Document uploaded |
|
PropertyDevelopmentDocumentDeletedNotification |
Team members |
Document deleted |
|
PropertyDevelopmentConstructionUpdateNotification |
Stakeholders |
Construction update posted |
|
PropertyDevelopmentCommentReplyNotification |
Mentioned / replied member |
Comment reply or mention |
|
|
Notification count The supplied specification identifies 23 targeted notification classes in this reference. Delivery channels and exact message content should be confirmed in the deployed environment. |
26 Backend Models Reference
|
Model |
Purpose |
|
PropertyDevelopmentProject |
Core project record: type, status, budget, dates and location. |
|
PropertyDevelopmentPhase |
Project phases, dates, status, budget and dependencies. |
|
PropertyDevelopmentTask |
Phase tasks, assignment, priority, status and due dates. |
|
PropertyDevelopmentTaskActivity |
Activity history for tasks. |
|
PropertyDevelopmentTaskTimeLog |
Time recorded against tasks. |
|
PropertyDevelopmentTeamMember |
Project staff, consultants, roles and status. |
|
PropertyDevelopmentRisk |
Risk register, probability, impact and mitigation. |
|
PropertyDevelopmentMilestone |
Key milestone tracking. |
|
PropertyDevelopmentConstructionUpdate |
Progress updates, type, percentage and media. |
|
PropertyDevelopmentBimModel |
BIM files, previews and model metadata. |
|
PropertyDevelopmentDocument |
Project documents. |
|
PropertyDevelopmentDocumentTemplate |
Reusable document templates. |
|
PropertyDevelopmentLegalDocument |
Project legal documents. |
|
PropertyDevelopmentComment |
Comments, replies, reactions and mentions. |
|
PropertyDevelopmentContractor |
Contractor registry. |
|
PropertyDevelopmentContractorBid |
Contractor bids and status. |
|
PropertyDevelopmentContractorEvaluation |
Performance evaluations. |
|
BillOfQuantity |
BOQ header, status and project relationship. |
|
BoqSection |
BOQ work section. |
|
BoqItem |
BOQ line item, quantity, rate and amount. |
|
PropertyDevelopmentUnit |
Development units for pre-leasing or sale. |
|
PropertyDevelopmentUnitApplication |
Applications for development units. |
|
PropertyDevelopmentUnitApplicationDocument |
Application documents. |
|
PropertyDevelopmentUnitImage |
Unit media. |
|
PropertyDevelopmentVirtualStaging |
AI-staged unit images and tours. |
|
PropertyDevelopmentMarketingCampaign |
Development campaigns. |
|
PropertyDevelopmentMarketingCampaignAsset |
Campaign media assets. |
|
PropertyDevelopmentMarketingChannel |
Campaign channels. |
|
PropertyDevelopmentMarketingPlatformIntegration |
External platform connection records. |
|
PropertyDevelopmentMarketingLead |
Marketing leads, score, status and notes. |
|
PropertyDevelopmentMarketingLeadDocument |
Documents linked to leads. |
|
PropertyDevelopmentFinancingLender |
Lender profiles. |
|
PropertyDevelopmentFinancingApplication |
Development-finance applications. |
|
PropertyDevelopmentRoiCalculation |
Saved ROI calculations. |
|
PropertyDevelopmentScenario |
Optimistic, base and pessimistic scenarios. |
|
PropertyDevelopmentScenarioVariable |
Assumptions and variables within scenarios. |
|
PropertyDevelopmentPaymentPlan |
Payment-plan records for bookings. |
|
PropertyDevelopmentPaymentMilestone |
Payment milestones linked to construction. |
|
PropertyDevelopmentBuildPlan |
Build-plan structures. |
|
PropertyDevelopmentTenantBooking |
Pre-lease or booking records. |
|
PropertyDevelopmentImage |
Project-level images. |
27 Controllers and Services Reference
|
Controller |
Main purpose |
|
LandlordPropertyDevelopmentProjectController |
Core project create, update, images, AI suggestions, completion and report export. |
|
PropertyDevelopmentController |
Project dashboard, risks, ROI, timeline and AI insights. |
|
LandlordPropertyDevelopmentController |
Portfolio overview, analytics, KPIs, predictions, filters and preferences. |
|
PropertyDevelopmentPhaseController |
Phase create, update and AI duration, risk and template support. |
|
PropertyDevelopmentTaskController |
Tasks, assignments, project context and task statistics. |
|
PropertyDevelopmentTeamMemberController |
Team records, AI team analysis, bulk actions and export. |
|
PropertyDevelopmentRiskController |
Risk register, statistics and currency conversion. |
|
BillOfQuantitiesController |
BOQ header, sections, items, versions, AI generation, import and export. |
|
ContractorManagementController |
Contractors, bids and evaluations. |
|
ConstructionProgressController |
Progress, milestones, reports, schedules, trends and AI analysis. |
|
BimIntegrationController |
BIM upload, viewer, preview, compare, export and download. |
|
PropertyDevelopmentDocumentController |
Project-document create, update, download and delete. |
|
MarketAnalysisController |
Location analysis, trends, comparisons and reports. |
|
RoiCalculatorController |
ROI calculations, saved analyses, AI insight and currency. |
|
ScenarioPlanningController |
Scenario creation, update, comparison and AI analysis. |
|
FinancingMarketplaceController |
Lenders, applications, metrics and AI recommendations. |
|
MarketingCampaignController |
Campaigns, analytics, integrations, AI optimisation and reports. |
|
LeadQualificationController |
Leads, scoring, notes, status, import and export. |
|
PreLeasingController |
Units, applications, lead quality, demand prediction and reports. |
|
VirtualStagingController |
AI staging, tours, comparison, export and batch generation. |
|
PropertyDevelopmentCommentController |
Comments, reactions, search, mentions and export. |
|
PropertyDevelopmentAIController |
Project summary, cost prediction, metrics, recommendations and AI chat. |
|
UnifiedDashboardController |
Combined project and market dashboard. |
|
TimelineVisualizationController |
Gantt timeline and AI optimisation. |
|
Service |
Purpose |
|
AIService (PropertyDevelopment) |
Core property-development AI intelligence. |
|
OpenAIService |
GPT-powered recommendations, chat and analysis. |
|
BoqAIService |
AI BOQ generation. |
|
ScenarioAIService |
AI comparison and explanation of scenarios. |
|
AIVirtualStagingService |
Virtual staging generation. |
|
RealTimeService |
Configured live market and financial data feeds. |
|
CurrencyConversionService |
Multi-currency conversion and display. |
28 Recommended Operating Rhythm
|
Frequency / event |
Recommended review |
|
Daily |
Review overdue tasks, high risks, new contractor bids, construction issues, new leads and application actions. |
|
Weekly |
Update phase status, timeline, milestones, construction progress, BOQ changes, project KPIs and team workload. |
|
Monthly |
Review budget vs actual, forecast cost, ROI, scenario assumptions, market trends, financing, campaigns and executive summary. |
|
At phase gate |
Confirm completion criteria, documents, cost position, risks and approval before moving to the next phase. |
|
At BOQ revision |
Create a version, document the reason, review rates and obtain approval. |
|
At contractor award |
Record evaluation, approval, final status and notification. |
|
At major delay |
Update risk, phase, tasks, milestone, construction report and stakeholder communication. |
|
At completion |
Close phases, tasks, risks, BOQ, models, documents, reports and actual completion date. |
29 Worked Example - Mixed-Use Development
|
|
Scenario Apex Developments creates 'Central Park Towers', a mixed-use project containing residential apartments, offices and retail units. The company uses Leaseora from concept and feasibility through construction and pre-leasing. |
|
Stage |
What happens |
|
1. Project creation |
The project is created with type Mixed-Use, approved budget, dates, location, images and Planning status. |
|
2. AI planning |
The team reviews suggested phases, timeline, risks, budget allocation, milestones and team structure. |
|
3. Phases |
Planning, Design, Approvals, Foundation, Structure, Services, Fit-Out, External Works and Handover are created. |
|
4. Tasks |
Design, procurement and construction tasks are assigned with dates, priority and owners. |
|
5. Team |
Internal staff, consultants and specialists are added and reviewed for capability gaps. |
|
6. Risks |
Planning approval, financing, material price and contractor capacity risks are logged and mitigated. |
|
7. BOQ |
The quantity surveyor creates the BOQ, reviews AI-generated content, creates versions and approves the baseline. |
|
8. Contractors |
Bids are recorded and compared with the BOQ; evaluations support the award decision. |
|
9. BIM |
Design models are uploaded, previewed and compared across revisions. |
|
10. Construction |
Progress, milestones, reports and delay notices are posted and reviewed. |
|
11. Feasibility |
Market analysis, ROI and three scenarios are updated using current cost, timing and demand information. |
|
12. Financing |
The company reviews lender options and tracks a financing application. |
|
13. Campaigns |
Marketing campaigns are created for residential, office and retail audiences. |
|
14. Leads |
Leads are captured, scored and progressed through New, Contacted and Qualified. |
|
15. Units |
Development units are defined with price, size, floor and status. |
|
16. Applications |
Qualified prospects submit applications; the team approves, rejects or waitlists. |
|
17. Virtual staging |
Residential and office units receive illustrative staged images and tours. |
|
18. Completion |
Actual completion is recorded, reports exported and the full activity history retained. |
30 Implementation and Onboarding Checklist
Data to prepare
|
☐ |
Project portfolio, project names, types, locations and descriptions. |
|
☐ |
Approved budgets, currencies, dates and baseline programmes. |
|
☐ |
Existing phases, milestones and task lists. |
|
☐ |
Team, consultant and contractor records. |
|
☐ |
Current risk register and mitigation plans. |
|
☐ |
BOQ files, rate schedules and cost summaries. |
|
☐ |
BIM models, drawings, permits, certificates and reports. |
|
☐ |
Market studies, ROI models and financing documents. |
|
☐ |
Marketing campaigns, channels, leads and unit inventory. |
People to assign
|
☐ |
Executive sponsor. |
|
☐ |
Project-development module owner. |
|
☐ |
Project manager and planner. |
|
☐ |
Quantity surveyor / cost manager. |
|
☐ |
Procurement and contractor manager. |
|
☐ |
Construction-progress owner. |
|
☐ |
BIM / design owner. |
|
☐ |
Document controller. |
|
☐ |
Finance / investment lead. |
|
☐ |
Marketing / sales lead. |
|
☐ |
Leaseora onboarding coordinator. |
Configuration to confirm
|
☐ |
Staff roles and permissions. |
|
☐ |
Currency context and conversion rules. |
|
☐ |
Project and phase status values. |
|
☐ |
Task reminder timing. |
|
☐ |
Risk-rating method. |
|
☐ |
BOQ approval and version process. |
|
☐ |
Contractor bid workflow. |
|
☐ |
Construction-report schedule. |
|
☐ |
Marketing-platform integrations. |
|
☐ |
Notification channels and recipients. |
31 User Acceptance Testing and Go-Live
|
Test area |
Acceptance test |
|
Project |
Create a test project, upload images, review currency and AI suggestions. |
|
Dashboard |
Confirm project and portfolio KPIs display expected values. |
|
Phases |
Create dependencies and verify timeline behaviour. |
|
Tasks |
Assign a task and test due-soon and overdue handling. |
|
Team |
Add and remove a member and verify notifications. |
|
Risk |
Create a high-risk record and verify escalation. |
|
BOQ |
Create sections and items, version, import and export. |
|
Contractor |
Record a bid and update the status. |
|
Construction |
Post general, milestone and delay updates and generate a report. |
|
BIM |
Upload, preview, compare and download a model. |
|
Documents |
Upload, update, download and test access control. |
|
Market |
Run a location analysis and verify source / freshness information. |
|
ROI |
Calculate and save ROI and compare scenarios. |
|
Financing |
Browse lenders and submit a test application where enabled. |
|
Campaigns |
Create a campaign and test an integration connection. |
|
Leads |
Import or create a lead, score and change status. |
|
Pre-leasing |
Create a unit and process an application. |
|
Virtual staging |
Generate, compare and export a test asset. |
|
AI assistant |
Generate summary, cost prediction and chat response. |
|
Completion |
Complete a controlled test project and export the final report. |
|
|
Pilot before portfolio rollout Start with one active project and a limited group of users. Confirm data quality, permissions, reporting and workflows before migrating the full development portfolio. |
32 Common Issues and Troubleshooting
|
Issue |
Recommended action |
|
Project dashboard appears incomplete |
Confirm phases, tasks, risks, team, budget and progress records have been entered and permissions allow access. |
|
Currency looks incorrect |
Review project country, currency context and conversion settings. |
|
AI phase or timeline is unrealistic |
Review project scope and data; treat the suggestion as a draft and adjust professionally. |
|
Phase shows overdue |
Check the approved end date and completion status. Record recovery action or approved baseline change. |
|
Task user cannot see assignment |
Review the team record, staff account and project permission. |
|
BOQ total is wrong |
Check item quantity, rate, section totals, import mapping and active version. |
|
Contractor quote cannot be compared |
Confirm bid items are linked to the correct BOQ or project. |
|
Progress percentage is disputed |
Review evidence and the company's approved measurement method. |
|
BIM preview fails |
Confirm file type, size, upload completion and viewer compatibility. |
|
Market data is stale |
Check the last refresh time and configured RealTimeService source. |
|
ROI result seems unrealistic |
Review costs, timing, revenue, financing and currency assumptions. |
|
Campaign has no live analytics |
Test the platform integration and confirm tracking permissions. |
|
Lead score seems inaccurate |
Review the lead data and use the score only as advisory. |
|
Virtual staging misrepresents the unit |
Regenerate using correct unit information and add disclosure. |
|
Project cannot be completed |
Check permission, actual completion date and unresolved required workflow items. |
33 Frequently Asked Questions
Can one company manage several projects?
Yes. The portfolio dashboard is designed to show multiple developments and project-level detail.
Can a project contain different development types?
Use the configured project type and detailed structure. Mixed-use projects can contain several unit types and commercial activities.
Does AI create the final project programme?
No. It proposes a draft. The project team approves the programme.
Can the BOQ be imported?
Yes. The supplied workflow includes Excel / CSV import and template support.
Can Leaseora compare contractor quotes?
Yes. Contractor comparison can review quotes against BOQ items.
Does BIM replace design software?
No. Leaseora stores, views and compares BIM information; specialist authoring remains in approved design tools.
Can the system calculate ROI in different currencies?
The supplied design includes CurrencyConversionService for multi-currency display. The company's financial assumptions still require validation.
Does the financing marketplace guarantee approval?
No. Lenders make their own decisions and terms must be reviewed.
Can projects be marketed before completion?
Yes. Campaigns, leads, pre-leasing, units and virtual staging support early commercialisation.
Can AI virtual staging be used in adverts?
Yes, subject to company approval and appropriate disclosure that the image is illustrative.
Can comments be used as formal approvals?
No. Use formal approval and document-control processes for contractual or governance decisions.
Can a completed project be reopened?
The supplied scenario does not define a reopen workflow. Confirm the production rule before relying on this.
34 Technical Matters to Confirm Before Production Sign-Off
|
Area |
Confirmation required |
|
Project status enum |
Confirm all production values and allowed transitions beyond Planning and Completed. |
|
Phase / task / risk statuses |
Confirm exact enum values and transition rules. |
|
Currency source |
Confirm project-currency logic, exchange-rate provider, refresh frequency and fallback. |
|
Real-time data |
Confirm market and financial data sources, availability, latency and licensing. |
|
AI providers and prompts |
Confirm service provider, model, data handling, logging and human-approval controls. |
|
BOQ calculation |
Confirm rounding, taxes, currencies, imports and version-locking rules. |
|
BIM support |
Confirm supported formats, file-size limits, viewer capability and storage. |
|
Financing applications |
Confirm required fields, documents, lender workflow and notifications. |
|
Marketing integrations |
Confirm supported platforms, authentication and analytics fields. |
|
Lead scoring |
Confirm scoring features, explanations and fairness controls. |
|
Unit application statuses |
Confirm exact states and reservation logic. |
|
Notification delivery |
Confirm email, in-app, push or other channels and retry behaviour. |
|
Document retention |
Confirm deletion, archiving, audit and legal-hold rules. |
|
Project completion |
Confirm prerequisites, automatic actions and whether reopening is permitted. |
|
Exports |
Confirm CSV, PDF, Excel or other supported formats for each report. |
|
|
Source basis This guide is based on the end-to-end scenario and technical references supplied for Leaseora. Items not explicitly defined in that material are identified for confirmation rather than assumed. |
35 Quick Reference - 25-Step Operating Flow
1. Create the project with type, location, budget, dates and Planning status.
2. Review dashboard, KPIs, predictions and initial AI insights.
3. Create project phases, dependencies and budgets.
4. Review and optimise the Gantt timeline.
5. Create and assign tasks within phases.
6. Add internal and external project team members.
7. Create and manage the risk register.
8. Create, import or AI-generate the BOQ.
9. Version, approve and activate the BOQ.
10. Register contractors and record bids.
11. Compare bids and record contractor evaluation.
12. Post construction updates and milestones.
13. Generate progress reports and reporting schedules.
14. Upload, preview and compare BIM models.
15. Upload and control project documents.
16. Analyse the project market and compare locations.
17. Calculate ROI, NPV, IRR and payback.
18. Create and compare project scenarios.
19. Browse lenders and submit financing applications.
20. Create marketing campaigns and platform integrations.
21. Capture, score and progress leads.
22. Create development units.
23. Process pre-lease or pre-sale applications.
24. Generate virtual staging and tours.
25. Complete the project, export final reports and retain activity history.
|
|
Business value Leaseora's Property Development module gives a real estate company one connected operating environment for feasibility, planning, cost control, procurement, construction, financing, marketing, pre-leasing and project completion. |
LEASEORA
PROPERTY DEVELOPMENT
Plan, control, finance, build and commercialise developments from one connected platform.
|
|
Support and onboarding For company-account setup, project onboarding, staff training or operational assistance, contact Leaseora through support@leaseora.com. |
leaseora.com